Step 1: Obtain an Ameren Missouri Permit

Ameren Missouri manages the shoreline of Lake of the Ozarks. You must secure a permit before making any modifications, including adding rip rap.

  • Application Submission: Complete the Ameren Missouri Permit Application.
  • Supporting Documents: Provide scaled drawings (maximum size 11"x17").
  • Review Process: Ameren Missouri evaluates for environmental impact and navigation safety.

Step 2: Secure Additional Approvals

Depending on the scope of your project, you may need additional permits:

  • U.S. Army Corps of Engineers (USACE): Required for work below the lake's normal water level.
  • Missouri Department of Natural Resources (MDNR): Ensures compliance with state environmental regulations.

Step 3: Comply with Permit Conditions

Once permits are granted, adhere to all conditions:

  • Construction Guidelines: Use approved materials and methods.
  • Time Restrictions: Perform work during specified times to protect wildlife.
  • Inspections: Prepare for regulatory agency inspections.

Step 4: Post-Installation Responsibilities

After installation:

  • Maintenance: Inspect and maintain the rip rap regularly.
  • Permit Renewal: Renew permits as required to stay compliant.